It takes Tom 2 days to paint a house and it takes Leah 4 days and it takes Lisa 6 days. How long will it take to paint the house together?
---------------
Tom DATA:
Time = 2 day/job ; Rate = 1/2 job/day
---------------
Leah DATA:
Time = 4 day/job ; Rate = 1/4 job/day
----------------
Lisa DATA:
Time = 6 day/job ; Rate = 1/6 job/day
------------------
Together DATA:
Time = x day/job ; Rate = 1/x job/day
---------------
EQUATION:
rate + rate+ rate  = together rate
1/2 + 1/4 + 1/6 = 1/x
Multiply thru by 12x to get:
6x + 3x + 2x = 12
11x = 12
x = 12/11 = 1 1/11 day (time needed to do the job together)
=================
Cheers,
Stan H.