Total labor required to do the job: 8*12 = 96 man-days.<br>
Amount of labor performed by 8 men in the first 3 days: 8*3 = 24 man-days.<br>
Amount of labor remaining: 96-24 = 72 man-days.<br>
Number of days required to perform the remaining 72 man-days of labor with 8+6 = 14 men: 72/14.<br>
ANSWER: 72/14 days to complete the job after the additional 6 men were employed<br>