Question 1200979
<pre>
A student makes bracelets and neckplaces starting on August 1st. She finishes a necklace every 6 days and a bracelet every 8 days. What is the first date on which the student will finish both a necklace and a bracelet? 
Correct answer: {{{highlight_green(matrix(1,5, First, "date:", highlight(matrix(1,2, 24^th, day)), of, month))}}} 

On the 24<sup>th</sup> day of month, the faster student will have finished 4 necklaces, while the slower will have finished 3 bracelets.</pre>