Question 1189492
.


The whole job is   6*10 = 60 man-days.


12 men will complete it in  &nbsp;&nbsp;{{{60/12}}} = 5 days.   &nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;<U>ANSWER</U>