7 men can dig a drain in 10 days. how many men would dig the same drain in 14 days
~~~~~~~~~~~~~~~~~~~~~~~


<pre>
The whole job is 7*10 = 70 man-days.


To complete the job in 14 days, 5 = 70/14  workers are needed.    <U>ANSWER</U>
</pre>