(a)  The entire job is  18*3 = 54 worker-days.


     12 workers will complete it in  {{{54/12}}} = 4 {{{1/2}}} days = 4.5 days.   <U>ANSWER</U>   <<<---===  edited after the notice by @greenestamps

                                                                    Thanks to @greenestamps (!)




(b)  If the number of worker decreases, the time to complete the job increases.    <U>ANSWER</U>