The first worker stuffs 125 shrimp an hour, 1000 shrimp/8 hours=125 shrimp per hour.


With a second worker, the 2 can stuff 200 shrimp an hour, because it is 1000 shrimp/5 hours, which is 200 shrimp an hour.

Since the first worker can do 125 shrimp an hour, the second worker must stuff 75 shrimp an hour.

So for 1000 shrimp/75 shrimp/hour, that will be 13.33 hours to do
.33 hours is 1/3 of an hour or 20 min.
So it is 13hr 20 min to do it