Question 1134493
Arlene's work rate + Andre's work rate = Team work rate

{{{1/2+1/3=(team work rate)^-1}}}

{{{3/6+2/6 = 5/6}}}

In other words, it would take them (5/6)^-1 for them to do the job together,
which means 6/5 hours.