Question 1103149
Rate x Time=Output.
.
.
.
{{{R[G]*8=1}}}
{{{R[G]=1/8}}}
.
.
{{{R[C]*6=1}}}
{{{R[C]=1/6}}}
So together,
{{{(R[G]+R[C])*2=(1/8+1/6)2=1/4+1/3=3/12+4/12=7/12}}}
So then,
{{{1-7/12=5/12}}}
{{{5/12}}} still needs to be done by Cherry.
{{{R[C]*t[C]=5/12}}}
{{{(1/6)*t[C]=5/12}}}
{{{t[C]=(5/12)(6)}}}
{{{t[C]=5/2}}}
Cherry needed {{{2&1/2}}} hours to finish.