Question 1101827
<br>
There are tons of different ways to solve this kind of problem.  I hope you get several solutions from different tutors so you can find the method that "works" best for you.<br>
Here is my preference for solving this problem.<br>
The amount of time has been reduced by a factor of 3/4; that means the number of men must be increased by a factor of 4/3.  Then
{{{6 * (4/3) = 8}}}<br>
It will take 8 men to do the job in 3 days.