Question 1101827
6 men dig a ditch in 4 days
they dig (1/4) ditch in a day.
In 3 days, they dig 3/4 a ditch.
If there are 4/3 the number of men, they would dig a full ditch in 3 days
That would be 6*(4/3)=8 men.