Question 1069992
The complete job requires {{{3*15=45}}}{{{eng-days}}}.
After 5 days, the engineers have only completed {{{3*5=15}}}{{{eng-days}}}.
So the 5 engineers will need {{{30}}}{{{eng-days}}} to complete.
That will require an additional {{{30/5=6}}}{{{days}}}