If it took 8 labourers 28 days to dig a trench,how long will it take 6 labourers working at the same rate to dig the trench? 
-----
# of days and # of workers are inversely related::
----
Equation:
d = k/w
-----
Solve for "k" using "8 laborers 28 days to dig.."
28 = k/8
k = 224
------
Equation:
d = 224/w
---
? how long for 6 workers ?
----
d = 224/6 = 37 1/3
----
Ans:: 38 after rounding up
----------