Question 985130
.
((16 workers)(6 days))/12 cupboards=8 worker-days/cupboard
It takes 8 worker-days to paint 1 cupboard.
.
((45 cupboards)(8 worker-days/cupboard))/12 workers=30 days
ANSWER: It will take 12 workers 30 days to paint 45 cupboards.