Question 978145
r, the one-man rate
{{{30r*15=1}}} for ONE JOB.
{{{highlight_green(r=1/450)}}}



THEY work for 5 days, and then  {{{30-5=25}}} of them continue to work to completion of the one job.


{{{highlight((30/450)*5+(25/450)*t=1)}}}