12 hrs/day for 12 days is {{{ 12*12 = 144 }}} hrs
4 hrs/day for 4 days is {{{ 4*4 = 16 }}} hrs
-----------------
{{{ 12 + 4 = 16 }}} m of tunnel
-----------------
12 persons dig 
12 m of tunnel in
144 hrs
-----------------
4 persons dig
4 m of tunnel in
144 hrs
-----------------
16 persons dig
16 m of tunnel in
144 hrs
-----------------
{{{ 9*16 = 144 }}} persons dig
16 m of tunnel in
16 hrs
-----------------
144 men are required 
To explain:
{{{ 16 = (1/9)*144 }}}, so to dig
the same number of tunnels in
1/9 the time, it will take
9 times as many men
---------------------