1 pipe will fill a container in 20 minutes, the second pipe will fill the container in 30 minutes, how long will it take to fill the conatiner with both pipes?
-----------------------

First pipe DATA:
Time = 20 min/job : Rate = 1/20 job/min
------------------
Second pipe DATA:
Time = 30 min/job ; Rate = 1/30 job/min
---------------
Together DATA:
Time = x min/job ; Rate = 1/x job/min
============
EQUATION:
1st pipe rate + 2nd pipe rate = together rate
1/20 + 1/30 = 1/x
Multiply thru by 60x to get:
3x + 2x = 60
5x = 60
x= 12 min/job (time required for pipes working together to do the job)
===================