A homeowner estimates that it will take her 9 days to roof her house. A professional roofer estimates that he could roof the house in 4 days. How long will it take if the homeowner helps the roofer?
=================
The owner does 1/9 of the roof per day.
The roofer does 1/4 of the roof per day.
Can you do the rest?