Question 926098
x = ali work rate (jobs/hr)
y = susan work rate (jobs/hr)
---
rate = work/time
time = work/rate
---
rate working together:
x + y = 1/9 + 1/5
---
time working together:
time = 1/(x + y) = 1/( 1/9 + 1/5 )
---
answer:
time = 3.21428571429 hours
---