Question 908123
A can complete a piece of work in 40 days and B in 60 days. A worked alone for 4 days and then B completed work along with c in 36 days. in how many days can C work alone to complete the work ?/
<pre>
B and C completed remaining {{{9/10}}} of job
Thus, working alone, C can complete work in {{{highlight_green(highlight_green(120))}}} days
You can do the check!! 