Question 903776
they were contracted to finish in 4 days 10*4=40 man days
but it took 5 days since they lost  a worker every day
so on the 4th day
day workers man days
1 10  10 
2 9  19
3 8   27
4 7  34
5 6  40 
equivalent to 10 workers for 4 days