Question 898577
10 men complete a job in 14 days
--------------------------------
1 man will take 10 times as long to do the job, so
-------------------------------------------
1 man completes a job in 140 days
----------------------------------------
4 men can complete the job in 1/4 of that time, so
---------------------------------------------
4 men can complete a job in 35 days