Question 850838
160 workers * 2 hours = 320 man-hours
320 man-hours produces 32 cars
Therefore, it takes 10 man-hours to produce one car.
.
220 workers * 3 hours = 660 man-hours
660 man-hours / 10 hours per car = 66 cars