Question 806193
10 men do 1 wall in {{{ 3*8 = 24 }}} hrs
-------------
Note that {{{ 15*8 = 120 }}} hrs
------------------
1/5 as many men will take 5 times as long 
to do 1 wall
------------------
So, 2 men do 1 wall in {{{ 5*24 = 120 }}} hrs
------------------
To do 3 walls in this time will take 
3 times as many men, so
---------------------
6 men can complete 3 walls in 120 hrs,
or 15 days  working 8 hrs a day