Question 801760
30 ft3 of cement is required to make a concrete floor that measures 90 ft2. 
30 ft^3 required for 90 ft^2
450/90 = 5
30 * 5 required for 5 * 90
150 ft^3 required for 450 ft^2
Hope this helps.
:-)