Question 61843

Suppose man A devotes 24 hrs, man B and man C each devote 30 hrs a week.
THen the job of 420 hrs needs 5 weeks to be completed by A, B and C.

24 X 5 = 120 hrs
30 x 5 = 150 hrs
30 x 5 = 150 hrs


Good Luck!!!