Question 615713
It takes 10 working days for 15 men to finish a painting job in certain warehouse. If there were 10 painters available and 5 of them could only work for half-day, how many days will it take to finish the job?
---

Job takes 10*15 = 150 man-days
5 full-time painters can do 5x man-days of the job
5 (1/2)-time painters can do (5/2)x man-days of the job
-----------------
Equation:
5x + (5/2)x = 150 man-days
(15/2)x = 150 man-days
x = 300/15 = 20 days total time to do the job
=============
Cheers,
Stan H.
===============