Question 552078
<br><font face="Tahoma">In order to solve this,<br>

we need to find out how many man-days it takes to plough the whole field.<br>

It is simple to see, that if it takes 8 men 9 days to do the whole job,<br>

then it will take them 9*8, or 72 man-days to complete the job.<br>

Now, we can find out how many days it would take 18 men to do the job.<br>

It would still take a total of 72 man-days to do the job,<br>

but this time, we have 18 men instead of 8.<br>

Simply divide 72 by 18, and we will have our answer.<br>

{{{72/18=4}}}<br>

Thus it would take 18 men only 4 days to plough the field.<br>

Algebraically, we would have written it:<br>

{{{18x=72}}}<br>

This type of problem is actually MUCH simpler to do than the ones involving filling pools and buckets.<br>

*******************************************************<br>

I hope this helps!  :)<br>

Email Scott: neatmath@yahoo.com for help with specific problems,<br>

or to inquire about mathematics tutoring via email or other methods.<br>

Paypal is always accepted for single problems or for more intensive tutoring!<br>

Single problems would range from 50 cents to 5 dollars each, depending on their complexity.<br><br>