The problems hinge on the fraction of work each can do per day, times the number of days.
.
(1/6 + 1/4 + 1/2)x = 1 whole job
.
(2/12 + 3/12 + 6/12)x = 1
.
11/12*x =1 
.
11x = 12
.
x = 12/11
.
So working together they can do the job in 12/11 of a day.
.