Question 502322
 a masons can build a 12 meters long wall in 4 days.
:
The number of man-days per meter requires: {{{(4a)/12}}} = {{{a/3}}} man-days per meter
:
:
find how many masons are required to build the 27 meters long wall in 3 days?
:
A 27 meter wall requires
27 * {{{a/3}}} = {{{(27a)/3}}} = 9a man-days
m = no. of masons required
3m = 9a
Divide by3
m = 3a
3a masons required to accomplish this