Question 470421
The Acme Class Ring Company designs and sells two types of rings:
 the VIP and the SST. 
The company can produce up to 56 rings each day, using up to 140 total man-hours of labor.
 It takes 7 man-hours to make one VIP ring and 2 man-hours to make one SST ring.
 Let x represent the number of VIP rings, and let y represent the number of SST rings.
 Including the system inequalities and, find the remaining inequalities that best describe this company's ring production.
:
No. of rings
x + y =< 56
:
Labor:
7x + 2y =< 140
:
x=>0
y=>0