twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop work. in how many days can the rest finish the work?
-----------------
The job is 24*38 man-days = 912 man-days
38*10 = 380 man-days done, 532 left
532 man-days/16 men = 33.25 days