Question 377443
Rate of bigger conveyor belt = 150 lbs/min
Rate of smaller conveyor belt = 50 lbs/min.
Let t = amount to finish the job with both conveyor belts working.
Then t(150 + 50) = 300, or 200t = 300, or t = 1.5 hrs.