Question 366781
If it takes 4 workers 6 hours each to pave a road, how many hours will it take 12
workers to complete the same job?

The answer is (A) 2

Solution 
Let x = the number of hours will it take 12 workers to complete the same job

12x = 4*6
  x = 2