Question 250482
C(x) = cost to produce all bicycles.
A(x) = average cost to produce one bicycle.


C(x) = 25*x + 20000


A(x) = (25*x + 20000)/x


C(250) = 25*(250) + 20000 = 26250


A(250) = 26250 / 250 = 105


C(250) = A(250) * 250 = 26250


Total cost to produce 250 bicycles is $26,250.