If Sally can paint the house in 4 hours, then she paints 1/4 of the house per hour.

If Jim can paint the house in 6 hours, then he paints 1/6 of the house per hour.

Therefore, when working together, their rate of work is {{{1/4+1/6 = 5/12}}} of the house per hour. Since they paint 5/12 of the house per hour, then they need 12/5, or 2.4 hours to paint the house together.


I hope this helps!