Question 204841
part B)
Since it takes 2 painters 5 hrs to paint 1 house, it would take the same 2 painters 100 hrs to paint 20 houses or 200 hrs for one painter.
So by dividing 200 by 10 (the aloted time) it would take 20 painters 10 hrs to paint 20 houses.