Question 176765
remember 1 cubic yd = 27 cubic feet
:
2500(12)=30000 sq ft
:
30000ft(3/4ft)=22500cu feet
:
so if we divide by 27 we will arrive at cubic yards
:
22500/27=833.33 cu yd's will be needed