SOLUTION: if 6 men can do a piece of work in 20 day who many extra men should be engaged to do the job in 15 days

Algebra ->  Human-and-algebraic-language -> SOLUTION: if 6 men can do a piece of work in 20 day who many extra men should be engaged to do the job in 15 days      Log On


   



Question 994648: if 6 men can do a piece of work in 20 day who many extra men should be engaged to do the job in 15 days
Answer by macston(5194) About Me  (Show Source):
You can put this solution on YOUR website!
.
x=number of men to do job in 15 days
.
%286_men%29%2820_days%29=%28x%29%2815_days%29
.
%28120_man-days%29=%2815_days%29%28x%29
.
%28120_man-days%29%2F%2815_days%29=x
.
8_men=x
.
ANSWER: Eight men can do the job in 15 days.