SOLUTION: Raja can do a piece of work in 20 days , while Ramesh can finish it in 25 days. ramesh started working and Raja joined him after 10 days. The whole work is completed in ?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: Raja can do a piece of work in 20 days , while Ramesh can finish it in 25 days. ramesh started working and Raja joined him after 10 days. The whole work is completed in ?
Log On
Question 994572: Raja can do a piece of work in 20 days , while Ramesh can finish it in 25 days. ramesh started working and Raja joined him after 10 days. The whole work is completed in ? Found 2 solutions by josgarithmetic, stanbon:Answer by josgarithmetic(39613) (Show Source):
You can put this solution on YOUR website! The piece of work is one whole, 1.
RT=1 , uniform rate equation for doing one unit of work, relating rate and time.
Let t be the time for Raja to help in finishing the job.
Work that ramesh did alone:
Work that ramesh and Raja did in combination simultaneously:
You can put this solution on YOUR website! Raja can do a piece of work in 20 days , while Ramesh can finish it in 25 days. ramesh started working and Raja joined him after 10 days. The whole work is completed in ?
-----
Raja rate = 1/20 job/day
Ramesh rate = 1/25 job/day
----
Equation:
10 days work by Ramesh + x days work by both = 1 job
----------------
10(1/25) + [(1/20)+(1/25)]x = 1 job
-----
(2/5) + [(5+4)/100]x = 1 job
---------
0.40 + 0.09x = 1
0.09x = 0.60
x = 6 2/3 days
-----------------------
Cheers,
Stan H.
----------