SOLUTION: if father done a job in 12 days and son done in 6 days?how many days they takes together to done this job?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: if father done a job in 12 days and son done in 6 days?how many days they takes together to done this job?
Log On
Question 987364: if father done a job in 12 days and son done in 6 days?how many days they takes together to done this job? Answer by Boreal(15235) (Show Source):
You can put this solution on YOUR website! In one day, father does (1/12) and son does (1/6)
Together, they do (3/12) of the job in 1 day.
1/(3/12)=4 days to do the job together.