SOLUTION: A job is expected to take 8 days if 6 person are employed.
How long would it <s>continue</s> take <s>of</s> if 2 persons are engaged?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A job is expected to take 8 days if 6 person are employed.
How long would it <s>continue</s> take <s>of</s> if 2 persons are engaged?
Log On
You can put this solution on YOUR website! 6 people x 8 days=48 person-days
48 person-days/2 people=24 days
ANSWER: The job will take two people twenty four days.