SOLUTION: 24 boys bikeill complete a piece of work in 18 days,2days after they started the work,8 more boys joined with them.in how many days all of them together finished work?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: 24 boys bikeill complete a piece of work in 18 days,2days after they started the work,8 more boys joined with them.in how many days all of them together finished work?
Log On
Question 979754: 24 boys bikeill complete a piece of work in 18 days,2days after they started the work,8 more boys joined with them.in how many days all of them together finished work? Answer by josgarithmetic(39630) (Show Source):