Question 979061: 24 men can plough 42 hectares of land in 14 days . How many days will it take 16 men to plough 64 hectares
Answer by josgarithmetic(39617) About Me  (Show Source):
You can put this solution on YOUR website!
r, rate for one man
t, unknown days count for question part

system%2824r%2A14=42%2C16r%2At=64%29