SOLUTION: a work have to be complete in 10 days but 280 worker after 3 days work they complete only 1/4 of work , how much worker are required for complete the work in 10 days
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: a work have to be complete in 10 days but 280 worker after 3 days work they complete only 1/4 of work , how much worker are required for complete the work in 10 days
Log On
Question 976761: a work have to be complete in 10 days but 280 worker after 3 days work they complete only 1/4 of work , how much worker are required for complete the work in 10 days Found 2 solutions by josgarithmetic, MathTherapy:Answer by josgarithmetic(39613) (Show Source):
You can put this solution on YOUR website!
a work have to be complete in 10 days but 280 worker after 3 days work they complete only 1/4 of work , how much worker are required for complete the work in 10 days
Working at the original rate, workers can complete the remaining of job in the remaining 7 (10 - 3) days.