if 12men can dig a pit in 5days. how many more men do you require to do the same work in three days?
Answer by
solver91311(24713)
(
Show Source
):
You can
put this solution on YOUR website!
I already did this one: Question 972997
12 can do the job in 5 days.
12 can do 1/5 of the job in 1 day.
1 can do 1/5 times 1/12 or 1/60 of the job in 1 day
1 can do 3 times 1/60 or 1/20 of the job in 3 days.
So 20 can do the whole job in 3 days.
John
My calculator said it, I believe it, that settles it