Question 968964: if 6 men take 18 days to complete the hauling jobs how many days would be required to complete this task if three additional men were hired? Answer by amarjeeth123(570) (Show Source):
You can put this solution on YOUR website! 6 men take 18 days to complete the hauling jobs
9 men will take 6*18/9=12 days to complete the job
Answer=12 days