SOLUTION: All members of a crew work at the same pace. If only 4 members of the crew are working, they complete the job in 18 days. How much time will it take all 9 members of the crew to co
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: All members of a crew work at the same pace. If only 4 members of the crew are working, they complete the job in 18 days. How much time will it take all 9 members of the crew to co
Log On
Question 963821: All members of a crew work at the same pace. If only 4 members of the crew are working, they complete the job in 18 days. How much time will it take all 9 members of the crew to complete the same job? Answer by macston(5194) (Show Source):
You can put this solution on YOUR website! (4 men)(18 days)=72 man-days
72 man-days/9 men=8 days
ANSWER: It will take 9 men 8 days to complete the job.