25 men dig a canal in 21 days. In how many days will 15 men dig it?
Answer by
macston(5194)
(
Show Source
):
You can
put this solution on YOUR website!
.
.
25 men x 21 days=525 man-days
525 man-days/15 men=35 days
ANSWER: It will take 15 men 35 days to dig the canal.