| Question 962901:  A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days, A left then B and C together completed the work in 10 more days. A alone can complete the work in?
 Answer by LinnW(1048)
      (Show Source): 
You can put this solution on YOUR website! Set a = the rate of A in (piece of work)/day b = the rate of B in (piece of work)/day
 c = the rate of C in (piece of work)/day
 Below is the equation for all three working together.
 ( 10 days ) * ( a + b + c ) = 1(piece of work)
 Next we have the equation were all work together for 4 days,
 then only B and C continue for 10 more days.
 ( 4 days) * ( a + b + c ) + (10 days)( b + c) = 1(piece of work)
 Since each left hand side is equal to 1 piece of work,
 we have
 ( 10 days ) * ( a + b + c ) =
 ( 4 days) * ( a + b + c ) + (10 days)( b + c)
 and
 10( a + b + c ) = 4( a + b + c ) + 10( b + c)
 10a + 10b + 10c = 4a + 4b + 4c + 10b + 10c
 combining terms
 10a + 10b + 10c = 4a + 14b + 14c
 Notice that we can rewrite the above as
 10a + 10(b + c) = 4a + 14(b + c)
 if we subtract 10(b + c) from each side
 10a = 4a + 4(b + c)
 subtract 4a from each side
 6a = 4(b + c)
 divide each side by 4
 6a/4 = (b + c)
 Recall
 ( 10 days ) * ( a + b + c ) = 1(piece of work) or
 10(a + b + c) = 1
 so
 10a + 10(b + c) = 1
 Now substitute 6a/4 for (b + c) and we have
 10a + 10(6a/4) = 1
 10a + 15a = 1
 25a = 1
 This means that A at rate a will take 25 days to complete the work.
 
 | 
  
 | 
 |  |  |